Requirements for various class of Contractors

  • Equipments & Facilities

    The following table illustrates the requirement of equipments and other facilities under various classes depending on the work category:

    Mandatory Equipment & Facilities Class A
    W1 W3 W4
    Class B
    W1 W3 W4
    Class C
    W1 W3 W4
    Excavator (or) Pay loader (or) (Motor grader for W1)
    1 1
    Truck (Truck or Tractor for Class C)
    1 1 1
    1 1 1
    1* 1* 1*
    Air Compressor
    1* 1* 1*
    1
    Road Roller
    1
    Survey equipments (Theodolite/Total Station)
    1* 1* 1*
    1* 1*
    Concrete mixer (10/7 cft) & (7/5 cft for Class C)
    1 1
    1 1
    1 1
    Vibrator
    1 1
    1 1
    1* 1* 1*
    Steel Shuttering Set (sft.)
    5000
    2500
    Water Pump
    1
    1
    Crane Truck
    1
    1
    Meggar
    1
    1
    1
    Max Puller
    1
    1

    Astarisk (*) means at least one among three categories

  • Human Resources

    The following table illustrates the minimum number of employees required in each class and category.

    Permanent Key Employees Class A
    W1 & W3 W4
    Class B
    W1 & W3 W4
    Class C
    W1 & W3 W4
    Manager
    1 1
    1 1
    1 1
    Graduate Engineer
    1 (Civil) 1 (Electrical)
    1 (Civil) 1 (Electrical)
    Diploma Engineer
    2 (Civil) 2 (Electrical)
    1 (Civil) 1 (Electrical)
    1 (Civil) 1 (Electrical)
    Accountant
    1 1
    1 1
    Diploma Engineer
    3 (Civil) 3 (Electrical)
    2 (Civil) 2 (Electrical)
    1 (Civil) 1 (Electrical)
    Minimum Number of Employees
    8 8
    6 6
    3 3

    * Class D contractor do not need any employees as the work sizes are usually small and manageable by the propietor himself.

  • Registered Office

    Class C and above contractors are required to establish a registered office which shall be physically checked.

  • Works in Hand

    Class A contractors are not allowed to take up not more than 5 works at once, while Class B and C not more than 3 works, whereas Class D can execute only one work at a time.

  • Financial Capacity and Track Record